April 23, 2025: Eric Langton Replacement Project Update (with video)

April 23, 2025

Construction on the new school continues to move forward, with several key milestones reached over the winter months. Yellowridge Construction has now completed the concrete placement for the building’s walls, columns, and main floor. Since January, steel columns, beams, and metal decking have been installed, and the steel superstructure is expected to be largely complete by the end of April.

In March, installation began on the steel studs for both interior and exterior walls. This framing allows plumbers and electricians to begin the “rough-in” stage of their work. The current focus is to complete the roof by the end of May.

In the meantime, off-site civil work along Edge Street and 121st Avenue is scheduled for completion in summer 2025.

Timeline Update

While the new school was originally scheduled to open in January 2026, the updated timeline now anticipates construction will be complete and school will be ready for occupancy by June 2026.

You can view our most recent .

Our vision
Our vision is for every individual to feel valued and for all learners to reach their potential.
Our mission
Our mission is to support all individuals in their development as successful learners, and as respectful, caring and responsible members of society.